Site Visits: Team Assembly and Critical Path

Not finding what you need? Email us at [email protected]

Critical Path

The critical path outlined below is designed with six months of runway time leading up to a site visit; It captures the essential tasks and responsibilities of each office in executing a successful site visit.  The timeline should be adjusted to your needs. 

 

Assemble the Admin Core Team

Site visit planning requires substantial administrative support across multiple functions, including: 

  1. Overall project management
  2. Video production (if videos are required)
  3. Coordination with the proposal team, agency, university leadership, and other administrative units
  4. Scheduling
  5. Coordination of the venue, catering, hotel, and transportation logistics
  6. Preparation of briefing materials and agenda documentation
  7. Developmental editing of site visit content. 

Several staff members should be engaged at the outset to scope and meet the specific demands of the visit.

 

Meet with the PI(s)

Upon receiving notice of a site visit date, the core administrative team should meet promptly with the lead PI. The purpose of this meeting is to align on roles, expectations, team availability, timeline, and immediate next steps.

The following topics should be addressed:

Site Visit Strategy & Basics

  • Confirm site visit date, time, and format (in-person, virtual, or hybrid), accounting for holidays and team outages.
  • Identify essential participants from the proposing team and university leadership, establishing clear points of contact for all units.
  • Discuss the reviewer feedback and the evaluation criteria to frame the site visit strategy.
  • Select and reserve the venue, determining logistical needs for technical A/V support, catering, and transportation.
  • Finalize the rehearsal schedule, identifying the format and number of sessions required for the full team.
  • Identify long-lead items early, including video production requirements, architectural renderings, or presentation coaching.
  • Confirm the budget and source(s) of payment
  • Estimate the funding required for the site visit and determine how to secure those funds.
    • Note: The lead institution typically carries the majority share of the planning. Any financial participation from partner institutions should be secured early and in writing. Physical and hybrid site visits can cost up to $50,000 at Columbia, so early budget planning is essential.
  • Outline a stakeholder engagement plan for preparation activities, including how and when industry partners, community representatives, and relevant government entities will be involved.

Intro Communications

Once the proposed speakers, support, and administrative team have been identified following the initial meeting with the PI(s), gather the relevant contact information and begin outreach to confirm participation and schedule the kickoff meeting. The first message to the broader team should come from the PI(s), with the admin team CC'd. This helps signal the importance of the site visit, establish the seriousness of the effort, and set expectations early.

This communication should be brief enough that recipients will read it carefully, but comprehensive enough to be forwarded within each participating organization to others involved in preparation, such as university leadership, research administrators, communications staff, and partner-institution colleagues.

At a minimum, the introductory communication should include:

  • Notice of the site visit and its timing
  • A brief refresher on the funding opportunity
  • The kickoff meeting date or forthcoming scheduling information
  • A high-level overview of site visit requirements
  • The location of shared planning materials
  • Confirmation of the recipient's role in preparation and participation
  • A request to identify any additional institutional participants who should be included
  • A confidentiality statement indicating that the site visit details should only be shared on a need-to-know basis.

Kickoff Meeting

Once participation has been confirmed, schedule the kickoff meeting promptly. This meeting should address the following:  

  • Officially launch the site visit preparation process and orient the entire team.
  • Prepare materials in advance, such as a short slide deck summarizing the proposal, funding opportunity, and major milestones.
  • Review the proposal and feedback at a high level, clarify expectations, outline roles, and identify immediate priorities.

A member of the administrative team should be assigned in advance to document key discussion points, decisions, and action items for distribution after the meeting. That follow-up is important, since the kickoff meeting should serve not only as an orientation session but also as the point at which planning shifts to active execution.

Following the kickoff meeting, the administrative team should work with the PI(s) and relevant participants to:

  • Collect availability and calendar constraints for major participants
  • Finalize the project calendar and begin scheduling against known deadlines and availability
  • Develop a detailed project timeline that identifies major deliverables, review points, rehearsal dates, and assigned responsibilities
  • Confirm participants and schedule critical preparation sessions, including the Red Team review, speaker coaching, Q&A preparation, rehearsals, and final run-throughs
  • Identify and reserve the site visit venue and any spaces needed for in-person rehearsals, recognizing that at least one rehearsal in the actual site visit space is advised
  • Confirm any anticipated shared expenses or financial participation in writing, especially where partner institutions are expected to contribute
  • Begin any parallel workstreams that require a long lead time, such as leadership engagement, communications support, video production, or travel coordination.